+420 596 614 750

Case study

Frýdek-Místek – PV 249 kWp – LED lighting and lightning protection

A layered energy project for a manufacturing site, where photovoltaics, new lightning protection and gradual replacement of lighting followed one another.

Anonymised reference · Frýdek-Místek · 2019–2023

From brief to result

How we approached the project

Challenge

An energy-intensive food production site needed to reduce consumption gradually, without splitting responsibility between several suppliers. At the same time, each new phase had to link safely to the technology already in operation.

Solution

The foundation in 2019 was a 249 kWp rooftop PV plant. In 2020–2021 it was followed by an upgrade of the lightning protection and, between 2020 and 2023, by a gradual replacement of lighting in individual parts of the site.

Result

The result is an integrated whole in which photovoltaics generate the site's own energy, LED lighting reduces its consumption and the new air-termination system protects the investment on the roof. One partner holds together the delivery, monitoring and aftercare.

At a glance

What the project means in practice

The company did not start with one huge intervention. First it began generating its own electricity, then it upgraded the roof's lightning protection and finally reduced lighting consumption step by step. Each investment therefore makes sense on its own while supporting the others.

Technical overview

Photovoltaic part
Rooftop PV 249 kWp, SolarEdge technology
Mounting structure
Krajiczech PMT
Building protection
Follow-on upgrade of the air-termination system in 2020–2021
Reduced consumption
Gradual upgrade of the site lighting in 2020–2023

Technical data

Diagrams that help explain the solution

The examples are based on design documentation for typical solutions. They explain the principle of the solution; specific documentation is always prepared according to the building, the operation and the grid connection conditions.

Illustrative plan of the PV panel layout and DC routes on the roof

How to read a rooftop PV drawing

Illustrative design diagram: on the drawing, the designer verifies the usable area, spacing, service corridors and the routing of DC cables. This is not the actual drawing of this specific project.

Project story

The context behind the result

01 · Gradual upgrade

Three measures, one long-term plan

The project did not start by trying to change the whole site at once. The first phase brought on-site electricity generation, the next addressed roof safety after the panels were installed, and the third gradually reduced lighting consumption in the production and storage areas.

The individual steps support each other: more efficient lighting leaves more generated energy for the production equipment, and the upgraded lightning protection reflects the new situation on the roof.

02 · Operation and care

The partnership continues after handover

The photovoltaic plant is remotely monitored and its operation is part of long-term care. Each phase was integrated into the existing site so that further development does not have to start from scratch.

The reference shows that an energy upgrade can be split into manageable investment steps while keeping one technical concept and one point of responsibility.

What matters about the project

Main benefits and technical conclusions of the project

one brand for energy generation, building safety and lighting

follow-on investments without losing control of the project

a reference example of long-term cooperation with an industrial client

249 kWp PV + upgrade of lighting and lightning protection

Anonymised case study of a completed XENIUM project.

Related references

More projects from the same segment

Three sites – PV 2 MWp – BESS 1,080 kWh

Long-built trust of a large retail chain, proven at three sites and extended with battery storage in a modified shipping container.

View the case study

Czech Republic – PV 192 kWp – BESS 226 kWh

An energy system for an operation where a power outage must not stop cooling and endanger the vacuum hardening equipment.

View the case study

Krnov – PV 218 kWp – BESS 416 kWh

A project for meat processing, where photovoltaics and storage protect continuous refrigeration and reduce costs at the same time.

View the case study

From a reference to your project

A similar result starts with an analysis of the specific operation