+420 596 614 750

Case study

Czech Republic – PV 192 kWp – BESS 226 kWh

An energy system for an operation where a power outage must not stop cooling and endanger the vacuum hardening equipment.

Anonymised reference · Czech Republic · published 2026

From brief to result

How we approached the project

Challenge

Vacuum hardening depends on precisely controlled water cooling. A power outage in the middle of a cycle can ruin the parts being processed and endanger the equipment itself, so the project had to deliver both savings and energy resilience.

Solution

XENIUM connected a 192 kWp PV plant with a 226 kWh indoor battery storage system operating in island mode. The BESS is intended primarily as backup for the water cooling; the project also included replacing the operation's lighting with LED.

Result

One project delivered on-site generation, backup for critical equipment and lower lighting consumption. The energy system thus reduces running costs while limiting the risk of damage during a grid outage.

At a glance

What the project means in practice

Here the battery is not just about savings. During a grid outage it must keep the water cooling of the vacuum hardening plant running so that neither work in progress nor the equipment itself is damaged.

Technical overview

Photovoltaics
192 kWp, east–west orientation
Battery storage
226 kWh, indoor installation
Operating mode
Island backup for critical water cooling
Other measures
Upgrade of the operation's lighting to LED

Technical data

Diagrams that help explain the solution

The examples are based on design documentation for typical solutions. They explain the principle of the solution; specific documentation is always prepared according to the building, the operation and the grid connection conditions.

Illustrative block diagram of a BESS battery storage connection

How the BESS is connected to the energy system

Illustrative design diagram: the battery container is connected to the distribution board and the distribution grid via the PCS power unit. The actual connection is always designed according to the power, operation and grid connection conditions.

Project story

The context behind the result

01 · Critical operation

Cooling must continue even during an outage

For a vacuum hardening plant, electricity is not just a cost item. It powers a process whose interruption can affect the entire batch in progress as well as the safety of the equipment.

That is why the battery was not designed just for time shifting. Its key role is to keep the water cooling running when the distribution grid is unavailable.

02 · Complete delivery

Generation, backup and energy-efficient lighting

Photovoltaics with east–west orientation spread generation over a larger part of the day. The indoor BESS stores energy and creates a backup layer for the critical equipment.

The LED lighting upgrade also reduced the site's own consumption. The project thus combines three different benefits, none of which works in isolation.

What matters about the project

Main benefits and technical conclusions of the project

an island system for a technologically critical operation

the battery as insurance against outages

a combination of savings and operational security

192 kWp PV + 226 kWh battery + LED lighting

Anonymised case study of a completed XENIUM project.

Related references

More projects from the same segment

Frýdek-Místek – PV 249 kWp – LED lighting and lightning protection

A layered energy project for a manufacturing site, where photovoltaics, new lightning protection and gradual replacement of lighting followed one another.

View the case study

Three sites – PV 2 MWp – BESS 1,080 kWh

Long-built trust of a large retail chain, proven at three sites and extended with battery storage in a modified shipping container.

View the case study

Krnov – PV 218 kWp – BESS 416 kWh

A project for meat processing, where photovoltaics and storage protect continuous refrigeration and reduce costs at the same time.

View the case study

From a reference to your project

A similar result starts with an analysis of the specific operation