+420 596 614 750

Case study

Carports: feasibility study

Feasibility study of photovoltaic carports as a basis for companies, municipalities and investors.

Anonymised reference · Czech Republic and Slovakia · July 2026

From brief to result

How we approached the project

Challenge

A carport is at the same time a structure, a generating plant and future transport infrastructure. Before deciding, the investor therefore needs to bring together the structure, foundations, electrical part, permitting, economics and preparation for charging and storage.

Solution

The study compared four size options from 50 kWp to 1 MWp, their required area and number of parking spaces. It covers the technical design, permitting procedure, investment model and options for extension with EV charging, BESS and EMS.

Result

The result is a decision-making basis for companies, cities and investors. A car park can be used for on-site generation without touching roofs or taking up more land, while preparing the site for the growth of e-mobility.

At a glance

What the project means in practice

The study first verifies how many parking spaces can be covered, what output fits on the structure and whether generation matches the building's consumption or EV charging. The investor thus gets a comparison of options before paying for the detailed design and permitting.

Technical overview

Options assessed
From smaller installations of around 50 kWp to site-wide systems above 1 MWp
Technical content of the study
Parking layout, load-bearing structure, cable routes, grid connection and any charging infrastructure
Energy balance
Comparison of generation with the consumption profile and options for using surplus energy
Output for the investor
Comparison of technical options, the investment framework and next steps

Technical data

Diagrams that help explain the solution

The examples are based on design documentation for typical solutions. They explain the principle of the solution; specific documentation is always prepared according to the building, the operation and the grid connection conditions.

Illustrative site plan of a ground-mounted PV plant and transformer station

What the site plan addresses

Illustrative design diagram: besides the panel rows, it shows the site boundary, the location of the transformer station and the connection route. This is not the actual drawing of this specific project.

Illustrative plan of the PV panel layout and DC routes on the roof

How to read a rooftop PV drawing

Illustrative design diagram: on the drawing, the designer verifies the usable area, spacing, service corridors and the routing of DC cables. This is not the actual drawing of this specific project.

Project story

The context behind the result

01 · A multifunctional structure

The car park becomes energy infrastructure

A carport protects vehicles from the weather while carrying photovoltaic panels. The basic design can include cable routes and reserves for future AC or DC charging.

Depending on the location, ground screws or concrete footings, the structural layout and the clearance height are chosen. The electrical part is designed according to the site's own consumption and grid connection options.

02 · Data-driven decisions

Four options for different site sizes

The model works with options of 50, 250 and 500 kWp and a 1 MWp solution. Each option combines the number of parking spaces, required area, expected generation and investment requirements.

The economics cannot be separated from the way the energy is used. Self-consumption, vehicle charging, a battery and energy management can change the operating benefit more than the size of the structure itself.

What matters about the project

Main benefits and technical conclusions of the project

suitable for companies, cities and investors

strong link to EV charging, BESS and electricity sharing

a clear comparison of technical options and investment scenarios before design starts

options from 50 kWp to 1 MWp+

XENIUM technical and economic feasibility study for photovoltaic carports.

Related references

More projects from the same segment

From a reference to your project

A similar result starts with an analysis of the specific operation